Read time: 30 seconds

  • An SOV is the line-item construction budget the lender approves before funding, and the scoring sheet every draw is measured against.
  • Organize by phase in build order — demolition, foundation, framing, mechanicals, finishes — with each line large enough to matter and small enough for an inspector to verify.
  • Front-loading is the #1 rejection reason. Pricing early lines above their true cost to pull cash forward breaks the draw model and gets the SOV kicked back.
  • Every draw traces to the SOV: percent-complete × budgeted amount, less retainage, less prior draws.
  • Include contingency (5–10%), soft costs, and the GC fee as their own lines — and total to the loan holdback exactly.

What a schedule of values actually is

A schedule of values is the line-item budget your construction lender approves before the first dollar funds — and the document every draw is measured against for the life of the loan.

On a purchase loan, the lender funds once at closing and is done. On a construction or heavy-rehab loan, the lender funds in stages as work gets completed, reimbursing you (or paying the contractor) for work that an inspector has verified. The schedule of values (SOV) is the map that makes that possible. It breaks the total construction budget into discrete line items — demolition, foundation, framing, roofing, mechanicals, finishes — with a dollar figure and a percentage of the whole assigned to each.

Two things flow from the SOV. First, the lender uses it at underwriting to sanity-check that your budget is realistic and that the as-completed value supports the total cost. Second, and for the life of the loan more importantly, every draw request is calculated against it: the inspector reports each line as a percentage complete, the lender multiplies that percentage by the budgeted amount, subtracts retainage and prior draws, and that is your check. A vague or front-loaded SOV does not just slow underwriting — it slows every single draw for the next nine months.

This article is the companion to how lenders verify percent-complete on construction draws. That piece covers the inspection side; this one covers the document that the inspection is scored against.

Anatomy of an SOV a lender expects

A lender wants the budget divided along the natural sequence of construction, roughly following the CSI division structure a general contractor already uses. Each line should be a trade or phase that an inspector can stand in front of and assess independently. Here is a representative SOV for a $180,000 gut rehab:

Line item% of budgetAmount
General conditions & permits5%$9,000
Demolition4%$7,200
Foundation & structural7%$12,600
Framing & rough carpentry11%$19,800
Roofing8%$14,400
Windows & exterior doors6%$10,800
Plumbing (rough + finish)9%$16,200
Electrical (rough + finish)8%$14,400
HVAC7%$12,600
Insulation & drywall7%$12,600
Interior finishes (paint, trim, flooring)14%$25,200
Kitchen & baths (cabinets, counters, fixtures)11%$19,800
Contingency3%$5,400
Total100%$180,000

Notice what this is not: it is not “rehab — $180,000” as a single line, and it is not a list of materials receipts. It is organized by phase, in build order, with each line large enough to matter and small enough to verify. A lender reviewing this can see at a glance whether the budget is plausible — framing at 11% and finishes at 14% are normal; demolition at 15% or contingency at zero would draw a question.

Front-loading: the #1 reason an SOV gets kicked back

Front-loading is assigning more value to early line items than the work actually costs, so that early draws release more cash than the completed work justifies. A contractor might price demolition at $20,000 and finishes at $11,000 when the true costs are reversed — pulling cash forward to fund their own working capital.

Lenders reject front-loaded schedules on sight, because the entire draw model depends on the lender never being “ahead” of the work. If $40,000 has funded but only $25,000 of verifiable work is in the ground, the lender is exposed: should the project stall, the collateral is worth less than what has been advanced. Retainage exists precisely to keep a cushion against this, but a front-loaded SOV defeats it.

The draw model only works if the money never gets ahead of the work. A front-loaded schedule of values breaks that invariant on the very first draw.

The fix is simple: price each line at its true cost. If your contractor insists on mobilization money, that belongs in the general-conditions line as a defined, modest percentage — not smuggled into demolition. A clean, honestly-priced SOV is the single biggest predictor of fast draws over the life of the project.

How the SOV drives every draw

Once approved, the SOV becomes a scoring sheet. At each draw, the inspector walks the site and reports a percent-complete for each line. The lender funds the newly-completed value, holds retainage, and nets out what it has already advanced. Here is draw two on the budget above:

Demolition — 100% × $7,200$7,200
Foundation & structural — 100% × $12,600$12,600
Framing — 60% × $19,800$11,880
General conditions & permits — 50% × $9,000$4,500
Total work completed to date$36,180
Less retainage held (10%)−$3,618
Eligible to date$32,562
Less Draw 1 already funded−$12,000
This draw (Draw 2)$20,562

Every number in that calculation traces back to a line in the SOV. If framing had been lumped into a single “structure” line with foundation, the inspector could not score it at 60% independently — and you would wait for the whole line to finish before releasing any of it. Granularity in the SOV is granularity in your cash flow. The retainage (here 10%) is released at the end once the project passes final inspection and any lien-waiver requirements are satisfied.

Contingency, soft costs, and the GC fee

Three line items trip up first-timers because they are real costs that do not look like “construction.”

Contingency. Lenders expect a contingency line, typically 5–10% of hard costs on a gut rehab. An SOV with zero contingency reads as a budget that has not been pressure-tested. Contingency is not free money — it draws only against documented change orders or overruns — but its presence signals that you have planned for the surprises every rehab produces. The 3% shown above is on the lean end; on an older property, underwriting may want more.

Soft costs. Permits, architectural and engineering fees, surveys, and inspection fees are soft costs. Some lenders fold them into general conditions; others want a separate soft-cost line. Either way, they belong in the SOV — leaving them out means paying them from your own pocket on top of the down payment you already budgeted.

The GC fee. A general contractor’s overhead-and-profit (often 10–20% of hard costs) is a legitimate line. The mistake is hiding it — spreading it invisibly across trade lines, which then read as overpriced and invite scrutiny. Break it out as its own line and it sails through.

Building one that gets approved

A schedule of values that clears underwriting on the first pass shares a handful of traits:

  • Organized in build order. Demolition before framing, framing before drywall, drywall before finishes. The lender should be able to read the sequence of the project off the page.
  • Each line independently verifiable. If an inspector cannot stand in front of a line and assign a percentage, it is too vague. Avoid catch-all lines like “miscellaneous” over a few percent.
  • Honestly priced, never front-loaded. Each line at its true cost. Mobilization money lives in general conditions, defined and modest.
  • Contingency present and reasonable. 5–10% on a meaningful rehab. Zero contingency is a red flag.
  • Soft costs and GC fee broken out. Not buried in trade lines.
  • Totals to the loan budget exactly. The SOV must sum to the construction holdback in the loan, to the dollar.

Build it once, build it clean, and the rest of the loan runs on rails. Build it vague or front-loaded, and you will re-explain it at every draw for the life of the project. If you want a second set of eyes before you submit, send your draft SOV with your loan file and our construction desk will flag anything likely to slow a draw before it becomes a problem.

Glossary

  • Schedule of values (SOV)

    The line-item breakdown of a construction budget, with a dollar amount and percentage assigned to each trade or phase, approved before funding and used to score every draw.

  • Draw

    A stage payment released as work is completed and verified, calculated against the SOV.

  • Retainage

    A percentage (commonly 10%) withheld from each draw and released at completion, protecting the lender against a stalled project.

  • Front-loading

    Assigning more value to early line items than they actually cost, to pull cash forward — a top reason an SOV is rejected.

  • General conditions

    Project overhead — supervision, mobilization, permits, temporary utilities — carried as its own SOV line rather than spread across trades.

  • Contingency

    A reserve line (typically 5–10% of hard costs) that funds documented overruns and change orders.

Frequently asked questions

Do I need a schedule of values for a small rehab?

If the loan has a construction or rehab holdback funded by draws, yes — even a light rehab needs an SOV so draws can be scored. The smaller the project, the simpler it is, but a single 'rehab' line is rarely accepted because nothing can be partially verified against it.

Who prepares the SOV — me or my contractor?

Usually the general contractor prepares it because they are pricing the trades, but the borrower owns it and submits it with the loan file. Review it before submitting; front-loading and missing contingency are things you can catch and your lender will catch.

How detailed does the SOV need to be?

Detailed enough that an inspector can assign a percent-complete to each line independently. Phase-level granularity (framing, roofing, plumbing, finishes) is standard. Receipt-level itemization is not required and slows review.

What percentage should contingency be?

On a meaningful rehab, 5–10% of hard costs is normal. Light cosmetic work can run lower; a gut rehab of an older property often warrants the higher end. Zero contingency reads as an untested budget and invites questions.

Why was my SOV rejected for front-loading?

Because one or more early line items were priced above their true cost to release cash sooner than the work justifies. Re-price each line at its real cost and move any mobilization money into a defined general-conditions line.

Can I change the SOV after it is approved?

Yes, through a change order. If a line runs over or scope changes, a documented change order reallocates budget — often drawing from the contingency line. Unilateral changes without lender sign-off will stall the next draw.

Does the SOV have to match the loan amount exactly?

It must total to the construction holdback exactly, to the dollar. The holdback is the rehab budget the lender is funding; the SOV is how that budget is allocated. A mismatch is an automatic kickback.

How does the SOV relate to percent-complete inspections?

The inspection reports a percent-complete for each SOV line; the lender multiplies that by the budgeted amount to compute the draw. The SOV is the denominator the inspection scores against — see our companion guide on percent-complete verification.

PML

PML Underwriting Team

PML underwrites and services its own construction and rehab loans nationwide. This guide reflects how our construction desk reviews a schedule of values and scores draws against it.

Want your SOV reviewed before you submit?

Send us your draft schedule of values with the property and scope, and our construction desk will flag front-loading, thin contingency, or vague lines before they slow a draw — so the first draw funds clean.

Contact us →